Artifact: Release Burndown Chart
The release burndown chart tracks a team's progress against its release plant.
Work Product Kinds: Scrum Work Products
Relationships
RolesResponsible: Modified By:
TasksInput To: Output From:
Description
Main Description

On a Scrum project, the team tracks its progress against a release plan by updating a release burndown chart at the end of each sprint. The horizontal axis of the release burndown chart shows the sprints; the vertical axis shows the amount of work remaining at the start of each sprint. Work remaining can be shown in whatever unit the team prefers--story points, ideal days, team days, and so on. 

On this burndown chart, the team started a project that was planned to be eleven two-week sprints. They began with 200 story points of work. The first sprint went well and from the chart you can infer that they had around 180 story points of work remaining after the first sprint. During the second sprint, however, the estimated work remaining actually burned up. This could have been because work was added to the project or because the team changed some estimates of the remaining work. From there the project continued well. Progress slowed during sprint 7 but then quickly resumed.

This type of release burndown chart works very well in many situations and in many teams. However, on projects with lots of changing requirements you may want to look at an Alternative Release Burndown Chart.